Skip Navigation
This table is used for column layout.
 
Minutes 12/18/2008
Municipal Renovations Committee  Minutes of Meeting  Thursday, December 18, 2008
MRC Meeting Minutes 12.18.08
Members Present: Ed Cook, Alan Zordan, Is Temkin, Bill Hill, Mayor Bingham, Mike  Clark, Tom Jerram  
Also Present: Stephen Nocera, Mayoral Aide; Lorel Purcell, O&G, Bob Roach and Brian  Solywoda, Friar Associates, Jerry Rollett, City of Torrington Public Works Director
1.The meeting was opened at 6:35 PM, on a motion from Mr. Zordan seconded by Mr.  Cook.             

  Mr. Clark reported that the temporary City Hall lease was approved by City Council,  with an addendum outlining handling of expenses specific to the construction of City  Clerk and Probate vaults. Mr. Clark stated that the City engineer, Ed Fabbri is in the  process of laying out the floor plan at Field Street and at this point is about 70%   complete. In addition,  all necessary  City  Hall employee tours have been completed.  Rudy Pullano has begun final planning pertaining to IT needs there.
Next steps for the MRC are to  finalize the seating plan, organize the moving procedure  to include identification of items to be moved, and to make certain that Mr. Pullano has  everything he needs to have communications systems up at the time of the move.
 A presentation of the 12.12.08 working drawing estimate was presented by Lorel  Purcell, Bill Hill and Bob Roach. Mr. Hill stated that it was his opinion that the project was on target to come in at or under the budget approved at referendum. Mr. Roach and  Mr. Solywoda stated that it was their opinion that the project was in an excellent position  with regards to budget. Both stated that in their experience most projects would be over  budget at this point and major  cost cuts would have to be  implemented. Mr. Hill agreed.  Ms. Purcell reinforced comments by Mr. Hill that the state of the economy including a  poor labor market and lower material costs were contributing factors to the lower cost  estimate, and that there were considerable savings from budget control of “Owner Costs”,  regulated by the MRC.  
 A discussion of the cost estimate was initiated by Mr. Clark. He asked the Committee  and all present to consider the 95% completion of  design carefully, stating that it would be the last opportunity to make major cost savings adjustments to the project without  incurring  costs associated with change orders and construction delays. Mr. Clark stated  that the budget savings projected included monies from contingency funds and not  definite cost savings verifiable by bids from contractors., and that until actual bids are  
reviewed it is premature to assume that the $200,000.00 budget savings currently  projected will come to fruition. Mr. Hill and Doctor Temkin felt that any changes made at  this point would seriously delay the bid/construction schedule affecting temporary City  Hall lease costs and construction costs. Mr. Clark stated that those costs would have to be  factored into any reviews proposed before changes could be evaluated. Mr. Clark asked  Ms. Purcell if abatement and demolition  could begin as scheduled  to allow work to start  on schedule. , and if scheduling of the project could catch up in a matter of weeks if  construction bids were not delayed beyond three weeks from the current  bid schedule.  She responded that that should be achievable.
Mr. Clark asked the members, and all present, to consider utilizing  space programmed to  be vacated by the relocation of the Probate suite of offices to the first floor  for use as the   Building Department. If this change were made, the need to construct the build -out addition to the third floor would be eliminated. Mr. Solywoda estimated that his  architects would need two to four weeks to modify all affected plans. The bid advertising   schedule  would then be delayed only two weeks from current plans. Ms. Purcell agreed  to have O&G’s cost estimator project the cost savings for this potential design change.  She felt that the analysis would be completed by Tuesday, 12/23. Mr. Hill and Dr.  Temkin opined that they were not in favor of making a major design change to the project  for reasons stated earlier in the meeting.  All other members and those present agreed that  cost savings should be evaluated and as soon as the cost impact was known a special  meeting of the MRC would be convened to decide what further action would or would  not be taken.


 Mr. Nocera stated that the commissioning contract had been approved by the City  Council on 12.15.08.


  Mr. Roach sated that next steps for Friar Associates were dependent upon design  decisions made by the MRC.


 Ms. Purcell stated that next steps for O&G were most immediately focused on  preparation of City Hall moving bid advertisements. She further stated that a walkthrough  of City Hall would be scheduled for Friday, January 9th at 1 PM. She asked that the City  Clerk be available to discuss his packing requirements. Mr. Nocera stated that all  personal property, i.e. that which would not be moved at  City expense, would be  identified with an “inventory dot”, prior to the walkthrough. Mr. Clark agreed to help  answer questions during the walkthrough. Ms. Purcell stated that bids would be due for  return to the City Purchasing Agent on January 19th.


 Under Other Business: Mr. Clark reported that the Republican American had agreed to  do a story on the Veterans Memorial and that Friar associates had furnished art materials  to support that effort. The story is tentatively scheduled to run the weekend following  Christmas.


 The meeting was adjourned at on a motion by  Mr. Zordan, seconded by Mr. Hill.
.